Purpose of writing this document is sometimes Actual Activity Cost does not get updated in KKBC_ORD against a production order. There are number reasons why activity cost not getting updated for production order as per SAP Note 380282 and the possible reason can be as below -
- The order must have a costing variant for actual costs (field CAUFVD-KLVARI).
- The confirmed operation must be relevant to costing (T430-KALKZ = "X"). This indicator is set in the operation control key.
- The order itself must have the "fully relevant to costing" attribute set (AFVGD-SELKZ = "X"). This indicator is copied from the routing and cannot be changed in the production order. For this, refer to SAP Note 378052, if necessary.
- The confirmed operation must have a work centre.
- The work centre must be assigned to a valid cost centre.
- In the work centre, a valid activity type as well as a formula must be defined for every activity whose costs you want to determine.
- These activity types also have to be specified accordingly in the order operation.
- For the activity types used in the work centre, the prices must be maintained for the cost centers of the work centre (transaction KP26).
- The confirmed operation must not be an external processing operation.
- During the confirmation, you must enter activities.